Heater Bands: Pre-Heat check list
PROCESS AIR & CUFF AIR:
- Verify the cool plug gasket is properly installed and seated
- For this system to work correctly this must be done!
- Verify the air lines are properly installed and connected 0
- For this system to work correctly this must be done!
- Verify if issues were found during cool plug and air line installation and the fixes made
- Clean air regulator/filter.
- Clean the proportion valves and filters.
- Ensure the die process air ports are clear.
- Verify the gap between cool plug and die is sufficient for cuff air flow.
- Note: the 48” cool plug must be installed with washers.
- Verify the functionality of the die process air ports by cycling through different air pressures while the corrugator mold blocks are positioned in the pipe forming zone.
- Note: Actual air pressures shown on the gauges won’t accurately represent the touch screen settings unless one is producing pipe
- Gauge should change with each setting change
- Verify the functionality of the cuff air by cycling through different air pressures while the corrugator mold blocks are positioned in the cuff forming zone.
- Note: Actual air pressures shown on the gauges won’t accurately represent the touch screen settings unless one is producing pipe
- Gauges should change with each setting change.